Community Corner

Construction Begins Monday on 15 Downtown Naperville Parking Lots

Maintenance begins Monday, May 5, and is expected to be completed by August.

The following press release was submitted by the city of Naperville:

The City of Naperville will be kicking off maintenance for 15 City-owned municipal parking lots as part of the Municipal Parking Lot Improvement Project, which will include work in several commuter and downtown parking lots throughout the summer.

Construction activity is scheduled to begin Monday, May 5, in several downtown lots. All work on all lots is anticipated to be completed by August 2014.

The Municipal Parking Lot Improvement Project includes maintenance that can range from minor work such as sidewalk replacement, curb and gutter replacement and patching to major repair work such as resurfacing and seal coating. The parking lots are located throughout Naperville and include the following downtown and commuter parking areas:

Find out what's happening in Napervillewith free, real-time updates from Patch.

Downtown: Van Buren surface lot, Riverview, Riverwalk, Central Parking Facility surface lot off of Jefferson Avenue, Central Park and Court Place

Commuter: Burlington Upper and Lower, Kroehler, Parkview, 95th Street Park-n-Ride

Find out what's happening in Napervillewith free, real-time updates from Patch.

The project will also include work at six fire station lots. Work will commence first in the downtown lots identified for improvements, with activity in the commuter lots taking place this summer.

For those lots slated for improvement within the month of May, below is an explanation of the work associated with each area.

Van Buren surface lot: Patching and restriping work is anticipated to take place beginning the week of May 5 and occur from 7 to 10 a.m. each day. Some temporary section closures will likely be necessary; however, at least one portion of the lot will remain open for use. After 10 a.m. each day, the lot will be open in its entirety to traffic and all parking spaces will be available for use.

Riverview and Riverwalk lots: Preliminary work will begin the week of May 5 and occur from 7 to 10 a.m. each day. Resurfacing work is anticipated to begin the week of May 12. The Riverview and Riverwalk lots will be completely closed for a 48-hour period once resurfacing work begins that week. Parking will be available in all other downtown lots during that time.

Central Parking Facility surface lot off of Jefferson Avenue: Preliminary work will begin the week of May 5 from 7 to 10 a.m. Monday through Wednesday. Patching will continue the week of May 12. Half of the parking spots will remain open while the patching takes place on the other half. Access to the Central Parking Facility parking deck will be maintained at all times.

Central Park and Court Place lots: Preliminary work will begin the week of May 5 from 7 to 10 a.m. Monday through Wednesday. Patching and restriping work will take place the week of May 12.

Information on work taking place in commuter lots later this summer will be posted to the City's website at www.naperville.il.us/downtownparking.aspx, at www.naperville.il.us/commuterparking.aspx, in the local media when possible and in some of the lots during construction.

Residents interested in knowing what construction projects are occurring this year can view the City’s Interactive Construction Map that lists upcoming major projects in the City, anticipated work schedules, and potential impact on the public. Residents can get regular updates by visiting the interactive map at www.naperville.il.us/mip.aspx. The interactive map allows users to type in an address to determine which capital improvement projects are happening in their area. By clicking on the icons and highlighted roads in the map, users can get information such as project details, projected work dates, description of the work being performed, potential travel impacts and current status. Users can also refer back to the project webpage for additional details on the project.

All construction is weather dependent; notice of schedule changes will be communicated using these same methods. Motorists are encouraged to sign up for the City’s new notification system Naper Notify to receive alerts on construction work such as this by visiting www.napernotify.com.

For more information on the City of Naperville, visit www.naperville.il.us. Sign up to receive the latest news on the City of Naperville’s projects and initiatives via email at www.naperville.il.us/enews.aspx.